Pre-Construction Notice – Watermain Replacement on Leland Ave. from Royal York Rd. to Fernalroy Blvd.

Posted in Construction Notices, Ward 5

 

 

The water service is the underground pipe that brings water to your water meter and is owned by you and by the City. The part you own is from your house to the end of your property, the part the City owns is from the end of your property to the watermain.

Expected Start Date: Summer 2018
Expected End Date: Fall 2018
Expected Permanent Restoration: Spring 2019
*Timeline is subject to change. Future notice to be provided

[READ] Pre-Construction Notice 

Six Points Reconfiguration – Construction Notice #6

Posted in Construction Notices, Road Work, Ward 5

 

 

The City of Toronto continues reconstructing the Six Points Interchange. Work is taking place southeast of Bloor Street West and Kipling Avenue (former Westwood Theatre lands), and at locations along Bloor Street West, Kipling Avenue, Dundas Street West, and Kipling access ramps.

Contract: 16ECS-Tl-01SP
Start Date: July 9th, 2018
Expected End Date: September 3rd, 2018
*Timeline is subject to change*

[READ] Construction Notice #6

Why You Need to Read the “Good Neighbour Guide”

Posted in Construction Notices, Development

 

 

Simply put, it’s a great go-to guide to understand your duty and role as: a resident being affected by residential development,
a contractor working on residential development or even a Ratepayer/Community group participant who assists your neighbourhood with applications.

This guide should be read through before filing complaints so that you are aware of the processes involved and can ask the right questions or file accurate complaints.

Although our office cannot interpret the guide, we surely can assist with your questions or else get City staff to respond accurately.

As seen in our July eNewsletter

Construction Noise Bylaw and Exemption Permits

Posted in City Wide, Construction Notices, Development, Ward 5

 

 

The Noise Bylaw provides standards for noise and applies to all properties in Toronto. The bylaw prohibits noise at any time that is likely to disturb others. Click here for more details.

The largest complaints are generally about construction, loud music or barking dogs.

Construction hours:

  • Monday to Friday between 7 a.m. and 7 p.m.
  • Saturday from 9 a.m. to 7 p.m.
  • not allowed on Sundays and statutory holidays

Exceptions to the rule:

Some construction projects apply for a noise exemption permit which allows them to work outside of the regulated hours.

Municipal work, or work undertaken due to emergency situations are exempt from the Noise bylaw and exemption requirements.

If possible, speak to the person or people responsible for the noise to give them an opportunity to correct the issue or of course contact our office. Alternatively, you should contact 3-1-1 Toronto with any complaint.

As seen in our July eNewsletter

INview + Other Helpful Construction Links

Posted in Construction Notices

 

 
We’ve shared this information in past eNewsletters but due to construction around the ward we wanted to ensure everyone has these helpful links. Please note these are all available on our website as well:

Toronto INview – Capital Project & Construction Notices for Planned Projects

Look up Toronto Construction projects – Ward Specific Interactive Map

Lake Shore Queensway Construction Projects

TTC Service Diversions Information

Toronto Road Restrictions

As seen in our July eNewsletter

Watermain Cleaning and Relining on Index Road

Posted in Construction Notices, Road Work, Ward 5

 

 

The City of Toronto will be cleaning and structurally relining the watermain in your area starting in the month of June. During this process, the City will also replace the City-owned portion of any substandard water service pipes.

Contract: 18TW-CTS-03CWD
Start Date: June 2018
End Date: November 2018
*Timeline is subject to change.

[READ] Construction Notice

Watermain Cleaning + Relining on The Queensway from The East Mall to Kipling Avenue

Posted in Construction Notices, Road Work, Ward 5

 

 

The water service is the underground pipe that brings water to your water meter and is owned by you and by the City. The part that the City owns goes from the municipal watermain to your property line. The part that you own goes from your property line to your water meter.

Contract: 18TW-CTS-03CWD
Start Date: June 2018
End Date: November 2018
*Timeline is subject to change.

[READ] Construction Notice

Road Resurfacing on River Valley Crescent + Other Local Roads [PRE-CONSTRUCTION NOTICE]

Posted in Construction Notices, Road Work, Ward 5

 

 

The City of Toronto is planning to replace damaged curbs and sidewalks and resurface River Valley Crescent, Fiesta Lane, and Tanglewood Terrace. Inspection of the road shows that it needs repaving and sections of damaged curb and sidewalk need to be replaced to bring them to a state of good repair.

Contract # 18ECS-TI-14LR
Expected Start Date: JULY 2018
Expected End Date: DECEMBER 2018
*Timeline is subject to change. Future notice to be provided.

[READ] Pre-Construction Notice