[JAN 2018 UPDATE] Road Resurfacing on The Queensway from High St. to West of Park Lawn Rd.

Posted in Construction Notices, Updates, Ward 5

 

 

[JAN 2018 UPDATE]

The project was delayed due to the strike that took place at the Food Terminal.  The new timeline for this project will be May – June 2018.

As seen in our January 2018 eNews

—-

[NOVEMBER UPDATE]

The resurfacing and boulevard work on the Queensway from High Street to 110m west of Park Lawn Road will be starting on November 8 and should be completed by December 22.  If crews are unable to do all the work there may be carry-over into 2018. We will keep you updated on our website and eNewsletter. 

Traffic Management :

Transportation Dept. has worked with the Work Zone Coordinator to ensure that  2 eastbound lanes are maintained during the morning rush hour.